The Dunn County 114th project is a 7-mile road reconstruction that began at the end of July and is expected to be completed by mid-November. Located near our Dickinson shop, just west of New Hradec, the project, at its highest had approximately 23 Baranko employees and 11 to 13 leased trucks on-site. In fact, many of the crew from Mountrail County have migrated over to this project.
Here’s a look at what’s been accomplished thus far…
September 12, 2024 : Pipe Installation
On the morning of September 12th, crews were busy grading and leveling the first 4 miles, while pipes were installed to control rainwater runoff.